A plan to turn a played-out coal mine into the largest solar farm ever built in Kentucky stirred the imaginations of clean energy advocates with a vision of hundreds of thousands of panels glinting on a thousand-acre wasteland, delivering clean energy to the power grid.
But a year after it was proposed, the $150 million project on Bent Mountain in Pike County, the heart of the state’s eastern coalfield, is still just a vision. Thanks to foot-dragging by Kentucky Fuel, a coal company that is years behind in a nearby cleanup that must come first, time may be running out for the solar venture.
“There is an urgency all the way around,” said Adam Edelen, one of the solar farm’s developers. “We feel it. This project being shovel ready in 2019 or 2020 is really important.” After that, federal tax breaks for renewable energy start to dwindle, undermining the economics.
“If Kentucky Fuel would do what they said they would do there wouldn’t be a problem,” said Edelen’s Kentucky partner, Ryan Johns, vice president of RH Group.
Four years ago, settling one of the largest enforcement actions in Kentucky’s recent history, the coal company’s owners promised state officials that they would compete a tangle of reclamation work spread over several counties by September 2015. But the case has dragged on in court. It’s a fight that involves one of the most powerful families in the region, headed by Jim Justice, the billionaire coal baron who is now governor of West Virginia.
It turns out that the shift from one of the dirtiest fuels to one of the cleanest can be a trickier business in coal country than in, say, corn country.
And in an ironic twist, both sides say paying for this transformation probably depends on digging up more coal where most of a mountaintop was already scraped away.
Unlikely Partners Join Forces on a Solar Farm
The solar project is a joint venture between unlikely bedfellows—EDF Renewables, an international developer of solar and wind energy, and Berkeley Energy Group, a coal mining subsidiary of the RH Group that is interested in diversifying. Berkeley is getting the land ready and works with Edelen, who developed the original concept with Berkeley and is working on finance and marketing.
Electricity from the 100-megawatt array would flow into the regional grid, but who would buy it—they’re looking for a big corporation—isn’t yet known.
“Our ideal will be a company that understands renewable energy is the future and a company that has a social impact value system,” says Edelen, a former state auditor.
Part of Edelen’s sales pitch, delivered in his mild Southern accent, is the solar farm’s location on a former mountaintop-removal coal mine in a part of the country where people are less likely to accept mainstream climate science, and where thousands of jobs have been lost as the nation has turned away from coal.
“The country needs people who sound like me talking about sustainability and climate change, and we need the environmental community to feel the urgency to rebuild coal country,” Edelen said. That includes green-minded companies.
“So many corporations are claiming the mantle of environmental leadership. This is a concrete way to do it,” he said.
Delays by Jim Justice’s Kentucky Fuel
Despite the setbacks, the developers still hope to begin construction by early 2019.
“This can be a speed bump, but it’s not a challenge we cannot overcome,” said Johns.
But Johns said he’s frustrated that a Justice family mining company, Kentucky Fuel, is years behind state-imposed deadlines to complete required reclamation work, including at a location near the proposed solar farm.
Kentucky Fuel’s attorney, Richard Getty, blames state regulators for slowing down the reclamation.
He filed a lawsuit last year claiming that the regulators, who were seeking to collect millions in fines from the Justice companies, chased away a mining and reclamation contactor with unspecified “willful and malicious” comments. The suit went after the personal assets of two state mining officials. Their agency, the Kentucky Energy and Environment Cabinet, called the lawsuit meritless. It remains unresolved.
Without going into details, Getty said reclamation work could resume soon.
The sooner the better, in the view of both the solar developers and the state officials.
What It Means to ‘Reclaim’ Bent Mountain
In 2014, Jim Justice reached a settlement with the Kentucky Energy and Environment Cabinet involving hundreds of reclamation violations in several of the state’s eastern counties. He agreed that by September 2015 his companies would reclaim 10 miles of what are known as “high walls”—what’s left standing after mountains are blasted to expose coal seams. Three miles of these have yet to be finished—including 2,700 feet of Bent Mountain, at a spot near the proposed solar farm.
John Mura, a spokesman for the state environment cabinet, said that one way or another, the Bent Mountain high wall needs to be restored to its approximate original contour.
That means bringing down the exposed walls, eliminating waste rock piles and restoring a landscape similar to what was there before, according to Kentucky regulations.
“We have been pushing Kentucky Fuel to reclaim that, and they have not done so,” Mura said. “And that’s one of the reasons we will be back in court on June 11.”
According to Johns, most of the high wall’s 2,700-foot-long face is on land abutting the solar site, and their fates are closely linked.
For one thing, the solar farm is designed to use rubble from reclamation to flatten out its own contours. For another, repairing the high wall involves more blasting, too close to allow the fragile panels to be installed until after it’s over.
More Coal Mining?
Kentucky Fuel wants more mining to help pay for the work.
“Other people might be interested in coming in there and doing some additional mining and reclamation,” said Getty, the lawyer for Kentucky Fuel. That’s a standard practice when there’s still coal available for recovery and it can be sold to help pay for the reclamation, he said. And the new waste rock gets used to re-shape the land.
But it is not clear whether valid leases are in place for that approach. That, too, may have to be sorted out; if not, the state could issue a permit for reclamation only, but the work would be more expensive.
It’s unclear whether the costs of additional reclamation, and the possibility of paying for it with more mining, would materially affect the solar farm’s construction costs. Delay itself can be costly in this kind of project, as state and federal incentives change.
“We are doing everything we can to make it as competitive as possible,” said Doug Copeland, who works in Philadelphia as regional development manager for EDF Renewables. “We are still very excited about it. My hope is that sometime later this year, we’ll have some real news on the project.”
The proposal “sounds like it would be of interest to companies that want to procure renewable energy if the price is right and if they want to tell a story of helping communities transition away from coal,” said Dan Bakal, director of electric power at Ceres, a Boston coalition of businesses and environmental groups.
“But it comes down to getting the price right to where it competes well with other projects that are out there,” he said.
veryGood! (274)
Related
- In ‘Nickel Boys,’ striving for a new way to see
- Tourist filmed carving his fiancée's name onto the Colosseum: A sign of great incivility
- Countries Promised To Cut Greenhouse Emissions, The UN Says They Are Failing
- NYC's Subway Flooding Isn't A Fluke. It's The Reality For Cities In A Warming World
- Nevada attorney general revives 2020 fake electors case
- A Wildfire Is Heading For Lake Tahoe, Sending Ash Raining Down On Tourists
- Kelly Clarkson Seemingly Shades Ex Brandon Blackstock in New Song Teaser
- Amid strife with Kremlin, Wagner Group mercenaries enter Russian city
- Trump invites nearly all federal workers to quit now, get paid through September
- Oregon Has A New Plan To Protect Homes From Wildfire. Homebuilders Are Pushing Back
Ranking
- Louvre will undergo expansion and restoration project, Macron says
- Lea Michele's 2-Year-Old Son Ever Is Back in Hospital Amid Ongoing Health Struggle
- TikToker Harrison Gilks Dead at 18 After Rare Cancer Battle
- The Dixie Fire Has Destroyed Most Of A Historic Northern California Town
- At site of suspected mass killings, Syrians recall horrors, hope for answers
- Harvard University Will Stop Investing In Fossil Fuels After Years Of Public Pressure
- JoJo Siwa Teases New Romance in Message About Her “Happy Feelings”
- Dozens injured by gas explosion at building in central Paris
Recommendation
DoorDash steps up driver ID checks after traffic safety complaints
Stunned By Ida, The Northeast Begins To Recover And Worry About The Next Storm
Climate Change Destroyed A Way Of Life On The Once-Idyllic Greek Island Of Evia
Hurry, Nordstrom Rack's Secret Dr. Martens Flash Sale Is Too Good to Miss
Selena Gomez engaged to Benny Blanco after 1 year together: 'Forever begins now'
The Western Wildfires Are Affecting People 3,000 Miles Away
Tom Schwartz Reveals the Moment Tom Sandoval Said He’s in Love With Raquel Leviss
Ava Phillippe's New Blunt Bangs Make Her Look Even More Like Mom Reese Witherspoon